The land on which the future plant will be built has an area of 41 hectares and the authorized value of the construction is 125 million lei, the mayor specified.

The land is located at the exit of Simeria, towards Alba-Iulia, at the intersection DN 66 with DN 7.

BSH will have to start the investment in the next 12 months and then has another 24 months to finish the execution. The deadline can be extended.

The mayor of Simeria also said that the local government will contribute to the success of this project by ensuring, until spring next year, the utilities networks - water and sewage, as well as access from DN 7 and DN 66 to the factory. (sorce: focus-energetic.ro)